Bankstown Airport Overlay

May, 2024
Bankstown Airport Overlay

- Project awarded 24th August 2023
- Project was completed April 2024

This project involves the re-asphalting of multiple taxiways within Bankstown Airport including the removal and reinstatement of associated Airfield Ground Lighting (AGL).
The summary of the scope is as follows:

  • Removal of AGL before pavement works including:
    - Removal, disconnection, and storage of existing AGL light fittings
    - Coring, removal, and storage of shallow base cans
    - Removal of secondary cable
  • Reinstatement of AGL after pavement works have been completed including:
    - Coring of taxiway for shallow base can installation
    - Installation of base can in cores using epoxy
    - Slot cutting of pavement for secondary cable installation
    - Reinstatement and reconnection of existing AGL light fittings and shallow bases
    - Reinstatement of cabling / conduits to each AGL light including sealing of joints.
    - Testing and commissioning
Bankstown Airport Overlay 3
Bankstown Airport Overlay 2
Bankstown Airport Overlay 1

Let's Get Your Project Started!

Avionics supply a wide range of Quality Aeronautical Ground Lighting Components from reputable high end companies including: